top of page

Construction Schedule & Activity Updates

Project Update: Week of February 16, 2025

Construction crews have been hoisting and positioning rooftop HVAC units and other equipment, while continuing to work inside the building to install elevators and insulation, as well as finish apartments and common areas. Apartment appliances are being installed, along with flooring, cabinetry and countertops.

roof (2).jpg
interior (2).jpg
counter.jpg
kitchen.jpg
insulation.jpg
hazard.jpg

General Schedule

The general contractor managing day-to-day activity on this project is Cranshaw Construction, based in Newton Lower Falls. Founded in 1983, the company has built more than 35 million square feet of space in Boston and its surrounding metro area. 

 

Construction is expected to be completed in March 2025. This page will provide regular updates on site activity.

 

Here is a general outline of what to expect in the months ahead:

 

September to December 2024 - In the final four months of 2024, crews working under the direction of Cranshaw Construction will be completing the structural framing for the building and making it weather tight so that work cam continue inside during inclement weather.

Permanent roofing will be completed, and dry wall will be installed, followed by painting and the installation of doors and flooring in choreographed sequence. The elevator and rooftop mechanical components also will be put into place, along with the installation of exterior siding.

Inspections to confirm that construction is adhering to Passive House environmental standards will continue throughout the process.

bottom of page